The Footings were excavated in good weather and filled with 8 cubic meters of concrete delivered by one cement mixer. David and Tom then spent 3 days putting in the footings which can be seen in the following images. the Footings have a 100 mm damp course and are 3 blocks deep, part of the damp course will be filled with cement before putting in soil pipes and cement for the under floor level.
View of the rear lean-To which will have the downstairs cloakroom, heat pump cupboard and utility room
View of the Side extension footings.
Side extension from the south of the Cottage
Another view of the rear extension